- District of Sheksna
- District of Cherepovets
- District of Chagoda
- District of Kharovsk
- District of Ustyuzhna
- District of Ust'-Kubinskoye
- District of Tot'ma
- District of Tarnoga
- District of Syamzha
- District of Sokol
- District of Nyuksenitsa
- District of Nikolsk
- District of Mezhdurech'ye
- District of Kichmengsky Gorodok
- District of Kirillov
- District of Kadui
- District of Gryazovets
- Vologda
- Cherepovets
- District of Vytegra
- District of Vologda
- District of Vozhega
- District of Verkhovazh'ye
- District of Veliky Ustyug
- District of Vashki
- District of Belozersk
- District of Babushkino
- District of Babaevo
Archive
Mass Media Overview
Severstal to build second ladle furnace at CherMK
23.11.2015 10:31
http://www.metalinfo.ru/en/
18 November 2015
Severstal, one of the world’s leading vertically integrated steel and steel-related mining companies, has begun construction of a second ladle furnace at the company’s flagship Cherepovets Steel Mill. The new furnace will have a capacity of 4.8 million tons. Launch of the construction was announced at Metal Expo 2015.
The aim of the project is to increase converter steel production to 84 meltings per day, or 10.283 million tons per year. Record annual converter steel production currently stands at 9.5 million tonnes.
Sergey Toropov, CEO of Severstal’s Russian Steel division, said: “The estimated cost of the project is around 3 billion rubles. Increasing production capacity by building a second ladle furnace will ensure that 100% of the smelting furnace treatment takes place within one unit. This will significantly reduce costs and improve product quality. It is estimated that the project will generate cost savings of around 700 million rubles per year”.
Completion of the furnace is scheduled for the end of 2017.