- District of Sheksna
- District of Cherepovets
- District of Chagoda
- District of Kharovsk
- District of Ustyuzhna
- District of Ust'-Kubinskoye
- District of Tot'ma
- District of Tarnoga
- District of Syamzha
- District of Sokol
- District of Nyuksenitsa
- District of Nikolsk
- District of Mezhdurech'ye
- District of Kichmengsky Gorodok
- District of Kirillov
- District of Kadui
- District of Gryazovets
- Vologda
- Cherepovets
- District of Vytegra
- District of Vologda
- District of Vozhega
- District of Verkhovazh'ye
- District of Veliky Ustyug
- District of Vashki
- District of Belozersk
- District of Babushkino
- District of Babaevo
Mass Media Overview
Power Station Krasavino ready for the start of trial run
30.07.2010 15:23
http://www.psg.cz
8.12.2009
The construction of 65 MW Power Plant for TEC Krasavino has reached the stage of Mechanical Completion and is ready to commence the Trial Operations. The project is being built by PSG-International – Power Division – in Krasavino, Vologda Region, Russia. This important project of total value of Euro 90 million would not be possible without an unprecedented support from the Ministry of Finance, Ministry of Commerce and Trade, Czech Export Bank and Egap, as well as other state organizations supporting Czech export. The official ceremony organized by our Client Vologdaoblkommunenergo, and its mother organization the Government of Vologda region, was on 15th December 2009 in Krasavino. TEC Krasavino is an excellent reference for our company, as well as for a number of Czech suppliers who were participating on this Project.
Ivan Vesely